| Name of Dam |
County |
Estimated Construction Costs
(millions) |
Construction Funding Status |
Project Status |
Additional Information |
| Belmont |
Wayne |
$1.4 |
PFBC – GG2 Funds |
PFBC engineering staff to design repairs. PFBC construction crews to perform modifications. |
nearby lakes |
lake info |
| Canonsburg* |
Washington |
$2.1 |
100% funded
1. H2o PA - $2.215 million |
Contract for repairs awarded. Expected completion in July 2012. |
nearby lakes |
lake info |
| Colyer* |
Centre |
$6.8 |
Unfunded |
Repair work not scheduled |
nearby lakes |
lake info |
| Donegal* |
Westmoreland |
$4.7 |
Unfunded |
Repair work not scheduled |
nearby lakes |
lake info |
| Dutch Fork* |
Washington |
$4.0 |
100% funded
1. H2o PA - $4.0 million |
Contract for repairs awarded. Expected completion in July 2012. |
nearby lakes |
lake info |
| Glade Run* |
Butler |
$4.3 |
Unfunded |
Repair work not scheduled |
nearby lakes |
lake info |
| Kyle* |
Jefferson |
$4.2 |
Unfunded |
Repair work not scheduled |
nearby lakes |
lake info |
| Leaser |
Lehigh |
$2.8 |
100 % funded
1. GBO - $1.8 million
2. DCNR/GG2 - $750,000
3. DEP/GG2 - $500,000
4. Lehigh County - $500,000 |
Contract for repairs awarded. Project is 85% complete. |
-- |
lake info |
Lower Hereford Manor*
Upper Hereford Manor* |
Beaver |
$12.0 |
100% funded Phase 1
1. H2o PA - $3.1 |
Dams to be breached as phase 1 of proposed future replacement project. Contract for breaching/repairs awarded. Phase 1 construction is 30% complete. Funding not yet identified for Phase 2 replacement. PFBC and local groups developed Phase 2 plans for the construction of a single replacement dam concept - $12 million. |
nearby lakes |
lake info |
| Lower Woods |
Wayne |
$1.8 |
PFBC – GG2 Funds |
PFBC engineering staff to design repairs. PFBC construction crews to perform modifications. |
nearby lakes |
lake info |
| Minsi* |
Northampton |
$3.1 |
Unfunded |
Repair work not scheduled |
nearby lakes |
lake info |
| Nessmuk |
Tioga |
$1.0 |
100% funded
H2o PA - $1.0 million |
PFBC engineering staff to design repairs. PFBC construction crews to perform modifications. |
nearby lakes |
lake info |
| Opossum |
Cumberland |
$3.3 |
100% funded
1. GBO - $1.45 million (Vance)
2. DEP GG2 - $609,000
3. Lower Frankford Twp. - $90,000
4. PFBC - $1.25 million GG2 |
Contract for repairs awarded. Project is 99% complete. |
-- |
lake info |
| Somerset* |
Somerset |
$5.0 |
Unfunded |
Repair work not scheduled |
nearby lakes |
lake info |
| Speedwell Forge* |
Lancaster |
$6.4 |
Unfunded |
Repair work not scheduled
(Speedwell Forge & other High-Hazard Dams presentation – Nov. 16, 2011 ) |
nearby lakes |
lake info |
| Stevens |
Wyoming |
$1.8 |
$0.00 |
Dam removed from HH list. Calculations certified by DEP that dam has capacity to manage 52% of Probable Maximum Precipitation (PMP). |
nearby lakes |
lake info |
| Virgin Run |
Fayette |
$4.2 |
$125,000 |
Removed from High-Hazard, unsafe list. Funding provided by PFBC for the acquisition of a downstream house. Family moved and PFBC researching easements to eliminate future development downstream from dam. |
nearby lakes |
lake info |